Piyushkumar Vahane

commissioning engineer, IAN Group sa
Turku, Finland

Umiejętności

Microsoft Office Microsoft Outlook 2007

Języki

hindi
ojczysty
angielski
biegły

Doświadczenie zawodowe

Logo
Commissioning Engineer at OL3 Finland Project
IAN GROUP SA
Plant Details: Olkiluoto 3 is the first EPR, which is a type of third generation PWR, to
have on going into construction. It will have capacity of 1600 MW. This is one of the
largest industrial projects ever carried out in Northern Europe.

Responsibility:
Responsible for Coolant treatment and process system,with other waste Auxiliary
systems.
Responsible for Commissioning Documentation and commissioning test Reports.
Closer all Open point from construction and planning for various commissioning
tests.
Hot / cold commissioning, valuable inputs for the control team.
Documentations like OTP, SOP, and Logics finalization for the plant.
Provides technical expertise auxiliary equipment applying precision maintenance
concepts that ensure equipment meets mechanical standards as required by
Statutory regulations.
Logo
Assistant Manager
Areva Solar India Pvt Limited -Areva Group
Rajasthan Sun techniques and private Ltd and reliance power Collaborated to setup a joint venture company, This is the first largest solar thermal power plant in the State of Rajasthan.

Plant Details:

125 MW Solar thermal based Power Plants, Areva make 26 TPH capacities Steam pressure 110 kg/cm2 once trough boiler (SSGs). Siemens makes 7 Extraction cum condensing turbine and their allied auxiliaries.

Fuels : Solar energy

Key Deliverables:
Operation & maintenance of 125 MW Solar thermal power plants.
Starting, stopping & operating of a boilers, and auxiliaries
Control total power plant from control room.
Steam blowing in drum less boiler.
Chemical cleaning activities.
Hot / cold commissioning, valuable inputs for the control team.
Commissioning activities.
Documentation like OTP, SOP, Logics finalisation for solar plant.
Involvement in controls and development team to make smooth solar operation.
Support engineering team to analysis and study solar fields.
Successfully commissioned and Asia’s largest solar CSP project in India
Successfully commissioned solar CSP boost up Project (TEP) in Tucson Arizona USA from Areva.
Finalize the training program for TEP operators and train TEP and AREVA operators for SSG operation in Arizona USA.
Identify all differences from an operation point of view between SSG and TEP boost SSG, and provide feedback to engineering team through technical note and commented operation procedure
Guide a support commissioning activities through punch point definition and classification; anticipate show stoppers and operational issues and provide inputs for activities time line in India and USA.
Operate the SSG for commissioning activities, start-up and ramp-up
Successfully perform performance test and commercial operation date for Indian and US project.
Logo
Engineer
Raj West Power limited- JSW ENERGY
Rajasthan State Minerals and Mining Ltd. and Raj West Power Limited have collaborated to setup a joint venture company, Barmer Lignite Mining Company Limited (BLMCL). This is the first and largest public- private partnership in the State of Rajasthan.

Plant Details:

8x135 MW CFBC Power Plants having DEC make 450 TPH x 8capacity Steam pressure 135 kg/cm2 and their allied auxiliaries 8x135 MW DEC (China) makes 7 Extraction cum condensing turbine and their allied auxiliaries.
Fuels : Lignite Coal

Key Deliverables:
Operation & maintenance of 135 MW thermal power plant of RAJWEST POWER LIMITED(JSW ENERGY)
Starting, stopping & operating (Normal as well as emergency) of a boilers, turbines and auxiliaries
Control total power plant from control room
Logo
Assistant Engineer
Aditya Cement Aditya Birla Group
Asst Engineer (Reporting to manager)

UltraTech is also the largest manufacturer of White Cement in India UltraTech is also the largest manufacturer of White Cement in India

Plant Details:

1x 23 BHEL make Turbine and 110 TPH x 1 capacity AFBC boiler Make BHEL 2x25 MW CFBC Power Plants having Thyssen Krupp make 125 TPH x 2 capacity Steam pressure 100 kg/cm2 and their allied auxiliaries.2x25 MW HTC (China) makes 3 Extraction cum condensing turbine and their allied auxiliaries.
Fuels : Indian Coal

Key Deliverables:
Operation & maintenance of 73 MW thermal power plant of Aditya Cement – Aditya Birla Group.
Starting, stopping & operating (Normal as well as emergency) of a boilers, turbines and auxiliaries
Control total power plant from DCS.
Logo
Control Room Engineer DCS operation
THERMAX LIMITED
Thermax Power Division, to its credit, has commissioned over 70 different projects in India and abroad. Thermax's rich experience in handling different types of fuels for its power plant projects include naphtha, gas, pet coke, biomass, coal, lignite, industrial waste gases and washery rejects.

Plant Details:

2 ×18 MW Power plant having Thermax LTD make 2 units of 80 TPH AFBC BOIER, 89 KG/CM², SHIN NIPPON Steam Turbine, PAHARPUR Air Cooled Condenser, Generator make TDPS are Controlled with WOODWARD Electronic governor and Honeywell C300 Controller Distributed Control system (DCS).
Fuels : Pet Coke, Bituminous (South African Coal, Philippines Coal, Vietnam Coal), Lignite.

Key Deliverables:

Operation of ,2x18MW Condensing Turbine and their auxiliaries
Safe Start up, Shut down activity of power plant.
Control total power plant from DCS
Logo
Operations Engineer
Bharat Petrolium Corporation Limited
74MW co-generation captive power plant with GE make frame V&VI 20×2MW Frame-V & 34×1 MW frame –VI Gas turbine

Fuels : GAS, HSD.

Key Deliverables:
To operate the Gas turbine with standard operating procedure.
Start up & shut down activities.
Emergency operation activities.
Fuel handling system (Naphtha).
Logo
Apprentice Trainee Engineer
Reliance Industries Limited
Plant Details:

48 MW combined cycle co-generation captive power plant with GE make frame -VI Gas turbine, capacity 34MW, (Mark-V speedtronic control system) & Steam turbine Skoda make 14MW with Trison Control system, HRSG DBBD make with DCS mode 300 control system .
Fuels : GAS, LDO, HSD.
Key Deliverables:

Operation of Skoda make turbine of capacity 16MW with its Auxiliary.
Operations of BHEL make gas turbine of 34mw capacity with its auxiliary.
Heat Recovery Steam Generation (HRSG) operation.
Hot and cold shut down procedure.
Charging of HP & LP boiler,
HP & LP boiler hydro test carried out.

Szkolenia i kursy

Diploma In Mechanical Engineering in 2004 from R.C.Technical Institute. INDIA

Edukacja

Logo
Mechanical engineer, inżynierskie
Karnataka State Open University

Specjalizacje

Inżynieria
Energetyka konwencjonalna i odnawialna
Inżynieria
Monterzy/Serwisanci